Saturday, October 30, 2010

October 2010

*Completed fire barrier fence / erected and painted.
*Security fence constructed in old shed erected on block.
*Land levelled and trenches dug for plumbing.
*Pipes necessary for concrete pour laid.
*Concrete pour after plumbing inspection.
*Shed erected to lockup stage.
*Switchboard for meter and solar feedback to grid mounted on adjacent building.
*Trench dug and water mains + Electrical mains Buried.
*Framing for toilet block erected / plumbing pipes installed.
*Main switchboard mounted and workshop lights wired and powered.
*4 Metre metal door constructed and secured in place.
*Framing for office,quiet room and store erected.
*Doors hung in all rooms.
*Store room walls painted.
*Fire hoses installed water connected.
*Cables for lighting in other rooms secured.
*Extra top hats and reinforced mesh installed in walls for stability and security.
*Ceiling joists and meeting room/kitchen framing erected.
*Cables installed for power points / water heater etc
*Trenches dug and pipes laid for sewer / inspection successful / trenches filled.
*All framing completed and frame inspection successfully carried out.
*During this time cluster and agency meetings attended and information stalls manned for Mental Health Week and Connect program. (Homeless and disadvantaged).
November 2010.